Jessica K October 6, 2015

Can you add story points in edit mode of the issue type instead of just in board view?

Can you add estimated and actual time in sub-tasks?

currently we do not have the option to do either of these.

Thanks

1 answer

0 votes
Deleted user October 6, 2015
1.) Yes, just add the "Story Points" in the "Edit Screen".
2.) Yes you can but not sure why you want points on sub-tasks as it always belongs to an a parent issue which should have the actual Story Points. Detailed answer here.

 

Jessica K October 20, 2015

1)How can you add the story points to the edit screen? 2) We need estimated and actual time tracking in sub-tasks, not story points.

Deleted user October 20, 2015

1.) Go to your Project Administration page, click on the appropriate "Screen Scheme" your "Story" issue type is associated to. Click on the screen that is besides the "Edit Issue" operation then add "Story Points" field 2.) Follow the steps above but add "Time Tracking" field instead.