With a Scrum board, does Jira Plan automatically populates the Target Start and Target End fields based on the sprint start and end dates when an issue is added to a sprint?
I noticed there's a setting under the plan configuration to "infer issue dates from sprint dates," but even with that enabled, the Target Start and End fields don’t appear to be updating in the plan.