Steven Choiniere October 22, 2020

Hello, 

 

I have created a filter that holds many Epics (over 200+), and I want to pull a timespent report for all tasks and subtasks within "My Epic Filter"

 

PLEASE don't say use Scriptrunner, I want a JQL query that can solve this without having to spend an absurd amount of money on a feature Atlassian should have already included. 

 

Thank you, 

1 answer

0 votes
Jack Brickey
Community Champion
October 22, 2020

no JQL option but what about this free option? Not sure if it will meet your needs or not but worth a go...

epic-sum-up-light 

Jack Brickey
Community Champion
October 22, 2020

also, maybe this could be done externally via Excel. you can use the Excel extension to run the query from your Jira project(s) right from excel and then calculate the total time logged.

Like Bill Sheboy likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events