Hi,
We are running JIRA 7.3 version. There is a ask to show the burn down chart with Hrs Vs Days for the sprint instead of story points Vs Days.
I don't see an option to change the default of Story points vs Days to Hrs Vs Days.
Could someone please let me know where to make the change for the Burndown.
Thanks
DP
Hi @DPA,
The documentation linked below should shed some light on how to alter the time tracking statistics:
The Burndown Chart is based on the estimation statistic. If you're using story points as your estimation statistic, the Burndown chart shows the story points per story (stories burning down the estimation statistic are only burnt down on the graph as they are completed). If you choose the time-tracking option, you're shown partial burndown (the number of hours currently used and remaining each day).
https://www.atlassian.com/agile/tutorials/burndown-charts
Hope this helps
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.