Hello community,
I'm upgrading a JSW Data Center with 2 nodes with ZDU. During and after the upgrade everything is OK
Upgrade node 1 and start Jira, starts in few minutes
Check the Cluster Activity : both nodes are active
Upgrade node 2 and start Jira : takes between 30 and 45 min to become active
Check Cluster Activity both nodes are active
Both Jira's can be accessed by their IP individually, and load balancing is OK
Why the second node takes 30 to 45min before becoming active ? logs stay idle
Any details about the background processes running ?
Notes:
- EasyBI runs on node2
- Upgrading Jira from 8.13.9 to 8.13.11