Hello community,
I'm sorry if I'm asking something already asked but I didn't find a response to my question.
I'm using Jira Plan and I'm using two different scenario in order to plan my initial planning and the current one.
I'm asking if there is a way to show the differences between these two scenarios (e.g. show issues that was planned to be closed on a specific date and that shifted ahead).
I'm also asking if there is a way to do this after saved the plan.
Thanks everyone for your precious help.
Ciao!
Hey Cristiano,
Currently, we don't have the option to compare different scenarios in a plan. There is an open suggestion ticket here: https://jira.atlassian.com/browse/JRACLOUD-88116
Please vote for this and add your comment on this ticket if you have any inputs.
Thanks!