In the filter I have selected "More" -> Open and completed issues AND selected "More"->Completed->Custom Date->Since 01/Jan/18.
I sometimes see Closed epics in one initiative I have, but another Initiative does not show the 2 closed epics.
Is there something I am missing for I validated the closed (resolved date) epics were within the 'Custom Date' specified above and the underlying stories.
I am stuck.
Thanks, Kathi
After investigating more on why some Epics that were closed were displayed and others did not, I found the reasoning to be
The plan will only show
Does anyone know of a workaround for it not displaying the Archived Versions? For our Initiative are normally 6 mths to a year and I don't want our Release Versions to be "Released" and still available from the screen drop-down (Fix Version).
Thanks, Kathi
If completed Stories won't have the Resolution, it won't show in the Portfolio plan but now sure how about Epics.