Currently our boards show the value for "Remaining" which is "Estimate minus Logged " just for the parent task, user story etc.
In an effort to break things down further, we have been placing estimates at the sub-task level - however, there appears no clean way to get the estimates and work logged associated with sub-tasks to roll up to the parent on the Jira board or backlog card. We were able to do this as a customized field on the card, but it's not ideal as it stretches out the length of the card.
Ideally I just want to replace the time in the bottom right of the parent to the value for "Remaining Sum".
How are other people handling this?
Here is an example of what I'm referring to.
-Dave
See if this https://jira.atlassian.com/browse/JRASERVER-70476 is what you are looking for. Vote and watch.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.