Jira Sub-tasks and displaying remaining sum instead of estimate on card

Dave Phillips January 25, 2019

Currently our boards show the value for "Remaining" which is "Estimate minus Logged " just for the parent task, user story etc. 

In an effort to break things down further, we have been placing estimates at the sub-task level - however, there appears no clean way to get the estimates and work logged associated with sub-tasks to roll up to the parent on the Jira board or backlog card. We were able to do this as a customized field on the card, but it's not ideal as it stretches out the length of the card. 

Ideally I just want to replace the time in the bottom right of the parent to the value for "Remaining Sum".

How are other people handling this?

Here is an example of what I'm referring to. 

-Dave

Untitled.png

1 answer

1 accepted

0 votes
Answer accepted
Alex Koxaras -Relational-
Community Champion
October 9, 2021

Hi @Dave Phillips 

See if this https://jira.atlassian.com/browse/JRASERVER-70476 is what you are looking for. Vote and watch.