Hi all, we use jira cloud, and are starting to try to use the timeline feature. We are hoping to show the parent epic of the pic based on the plans hierarchy. Is this possible or is timeline Epic -> Story/Task/Bug only.
Also is plans the only alternative to show multiple projects? Its a bit iffy that Boards will have a backlog of 2 projects, but then its connected timeline does not.
Hello,
Welcome to Community :)
The timeline is where you can create, manage, and visualize work from a board. This can be used only from single project .
Please find details here : https://support.atlassian.com/jira-software-cloud/docs/create-manage-and-visualize-work-on-the-timeline/
if you want to include data from multiple projects then jira plans would help here : https://support.atlassian.com/jira-software-cloud/docs/get-started-with-advanced-roadmaps/
Thank You,
Prachi
Thanks Prachi, I appreciate you confirming the above :D
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Calvin
The Timeline option that shows as a tab along side of Board, List, Summary, etc. can show only Epics and their children. The Timeline available in a Plan, or a third party app, must be used to see the extended work item hierarchy.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Trudy! I appreciate it, its good to know so I don't continue down the wrong rabbit hole trying to find a setting that doesn't exist.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.