Jira automation to rollup subatsk's minimum planned start date to its parent.

Shivaprasad Hattaraki October 7, 2022

Use case:        Story                   --> Planned start date = 08/Oct/2022

                       Sub-task1           --> Planned start date = 01/Oct/2022

                       Sub-task2           --> Planned start date = 04/Oct/2022

 

 

I want to compare Story and Subtask's Planned start date and update the earliest date of the subtask into Story if the Story date is greater than the subtask's date.

In the above use case: I want to roll up  sub-task1's planned start date in Story Type.

1 answer

2 votes
Walter Buggenhout
Community Champion
October 8, 2022

Hi @Shivaprasad Hattaraki and welcome to the Community!

Have a look at this related question. It pretty much covers your use case, I believe.

Hope this helps! 