Jira searh issues using JQL for on-track issues

prabu m October 24, 2019

I need to list out all the on-track issue in epic wise

We have an Epic and each epic have 'n' number of task, with a time estimate, so I need to list out all the on-track issues in each epic wise.

on-track = Time spent<=Original estimate

 

1 answer

1 accepted

0 votes
Answer accepted
Tansu Akdeniz
Community Champion
October 25, 2019

Hi @prabu m ,

Normally, you can use workratio feature on jira queries.

Ex;

  • workratio < 100 means timespent < Original Estimate
  • workratio = 100 means timespent = Original Estimate
  • workratio > 100 means timespent > Original Estimate

But, if you track over the epic, there is a free Epic Sum Up Light add-on which may help you to track total progress.

Regards

prabu m October 25, 2019

Hi @Tansu Akdeniz Thank you so much

Tansu Akdeniz
Community Champion
October 25, 2019

You are welcome @prabu m 