How do I get the Kanban board to show the tasks by assignee?
I had another project where this was the default view but with this new project it sorts them by expedited tasks and everything else. All tasks other than 2 fall under everything else.
I have looked in settings but have not been able to find a way to change this.
Hi @Andrea Poston ,
Welcome to Community !
Go to Board > Board Settings > Swimlanes > Select Assignee