Kanban board view

Andrea Poston November 20, 2019

Hello,

How do I get the Kanban board to show the tasks by assignee? 

I had another project where this was the default view but with this new project it sorts them by expedited tasks and everything else. All tasks other than 2 fall under everything else.

I have looked in settings but have not been able to find a way to change this. 

 

 

1 answer

1 vote
Avinash Bhagawati _Appfire_
Community Champion
November 20, 2019

Hi @Andrea Poston ,

Welcome to Community !

Go to Board > Board Settings > Swimlanes > Select Assignee

https://confluence.atlassian.com/jirasoftwarecloud/configuring-swimlanes-764478010.html

To configure this you need to have Board administrator permission.

Thanks,

Avinash

Andrea Poston November 20, 2019

Perfect! Thank you so much!