I'm using Advanced Roadmaps, and I have two problems (I'm using sprint dates in my scheduling configurations):
In the above image, you can see the most bottom issue, which starts at some point inside sprint 29, and ends inside sprint 30. I was expecting the selection to be limited to sprints only, as a story is bounded to a specific sprint.
Another example:
What's the meaning in this case of setting an issue to "random" date that's not bounded to a sprint? How to make sprint update when I move issues in the timeline?
Am I missing something?