Hi @Pradeep
The maximum number of tasks loaded in App Configuration >> Modules >> Gantt allows to specify how many tasks will be displayed on the Gantt chart at once. Once this number was exceeded, the “load more” button appeared.
However, please be informed that we have removed this option in the latest BigPicture version, and currently, Gantt loads tasks automatically as the screen is scrolled.
Maximum tasks to load in App Configuration >> Advanced >> Technical info allow you to specify the maximum number of tasks in each Box scope. There is no maximum limit.
Both fields refer to app Performance. More information you will find in our article: BigPicture Sizing Guide.
Best,
Anna