Hi Team

 

I am having one server jira instance,6.3 DB Mysql 5.6.22 and i need to move to cluster data center 8.23 postgreSql

Couple of question i have

I am looking for documentation which can guide me to migrate between server and datacenter.

few links are suggesting Jira data center migration App but i cannot use it because my source is on 6.3 and database is also Mysql. according to Jira data center Migration source should be above 7.13 and database should be postgreSql

 

Do i need to upgrade my source instance before i perform migration? or can i use "Project configuration for Jira" third party add on

 

Please advise

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 9, 2021

The main docs start at https://confluence.atlassian.com/adminjiraserver/migrate-from-server-to-data-center-993929572.html

But.  Yes.  You really should upgrade the Server, ideally to 8.13 (long term release version) or 8.18 if you want to run with the latest.

Go from 6.3 -> 6.4 -> 7.0 -> 7.13 -> 8.13/18 - you might be able to get away with not doing the 6.4 upgrade, but do not skip the 7.0 step - going higher than 7.0 from 6 is known to break your data in "interesting" ways.  

7.0 straight to 8.something is a right pain too.  Although it does not break stuff, it can take five or six times as much effort as 7.0 -> 7.13 -> 8.5 in my experience.