Migrating from server to data center, how can I take across Big Picture set up as well. I can find no pages that give me a process of how to do this. Big Picture 8.2.2 / Jira Software 8.13 server to Jira Software Datacenter 8.20
Hi @Fred W
Anna, using your exact instruction given in the link above the dump fails at step 1.2, just gives us a "big picture crashed" screen. Any reasons for this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Fred W
Pinpointing the exact cause requires deeper dive into your instance setting. I recommend raising a ticket via our Service Desk so that our extremely helpful Technical Support Team will investigate your case individually and provide you with a solution.
Please attach Jira logs to the ticket.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Fred W ,
because all big picture data are stored at DB level, no actions are necessary in order to migrate its data from server to data center if you perform a manual upgrade.
https://confluence.atlassian.com/adminjiraserver/upgrading-jira-data-center-manual-938846951.html
Hope this helps,
Fabio
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
are you able to backup your current DB and restore it in the new location?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.