Migration from a team-managed project to a company-managed project more than 4000 issues

Yulia Didan August 1, 2022

Dear All,

Could you please advice what is the best way to migrate the issues from the team-managed project to the company-managed project when there are more than 4000 issues. Would it be kept the same order in the new company-managed progect. And what could be the other risks.
Many thanks. 
Yulia

1 answer

1 vote
Robert Wen_Cprime_
Community Champion
August 1, 2022

The only way I know to migrate issues from a team-managed project to a company-managed project is through a bulk move to the new company-managed project.

Order is probably going to be dictated by how you have your list of issues ordered from the search.

I'd make sure the workflows between the older team-managed project and the company-managed project are as identical as possible to make remapping statuses easier.

Hope this helps