Hoping some folks can provide some advice. New to Jira...
I created a Jira project that would blend the views on two different Jira boards for a dev project with two versions that are currently being developed in parallel (this was done before Plan was upgraded AND before I has time to learn more about the tool).
Tickets were created in the backlog of the blended project view that are not showing on the individual project timelines (which makes sense because the boards are not connected). How can I move/reorganize/modify those tickets to populate the proper timeline for the associated project board?
Thank you!!