Have seen something that I don't think is correct. When you move an issue to another project but the issue is in an active sprint it brings the sprint across to the new project. This does not seem correct. I would have thought it would have no sprint? This can mean a scrum board has multiple sprints running..
Hi Paul
This is actually an expected behaviour as explained below:
Because Agile Boards are cross-project, they need to be able to display Sprints that span all issues (from multiple projects) that are displayed on that board.
To work around this, please remove the issue from the Sprint it is in before moving it to the new project. This can also be done after it is moved by looking at Plan Mode, right-clicking the issue, and choosing "Remove from Sprint".
Discuss in here before: https://jira.atlassian.com/browse/GHS-8168
Hope it helps !
Cheers :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.