Hell,
I have an Active sprint (Sprint 1) which needs to be closed but an issue in progress column has work logged against it
If I move this issue from sprint 1 to backlog and then into another sprint - Is reporting from sprint 1 affected I.e. time spent and a count of issue
Kind Regards
Helen
Hi @Helen Pippard ,
When you complete the sprint, your open issues will be moved into the location you specify (another sprint or the backlog).
Issues that run across multiple sprints will by default be associated with all the sprints they were in.
There is different behaviour when you report on issue count vs time spent. With issue count, burndown is only affected when an issue reaches the rightmost column of your scrum board. So an issue in progress will not be shown on the burndown line. With hours spent, you should see the burndown at the moment of hours being logged. So there's different behaviour there. But as long as your issue remains in both sprints (the default behaviour), then there should be no impact on your report.
Thank you so much for taking the time to respond.
Much appreciated
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.