Moving issues from a project to another only one issue-type option

DEJU ALIN MADALIN January 20, 2022

Hello,

I'm facing right now with an issue when I'm trying to move an issue from Project A to Project B. (I have all the necessary rights - jira-administrator).

 

Steps to reproduce:

1. From View Screen of the issue that needs to be moved (from Project A)-> More - > Move

2. I'm choosing Project B and at "New Issue Type" allows me to move to only one issue-type, not all the issues available in Project B.

Note* This is happening only when I'm trying to move issues from Project A, not for all the projects from the server.

 

Could you please let me know which can be the issue?

 

Thank you !

Best regards, 

Alin

3 answers

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 21, 2022

>"New Issue Type" allows me to move to only one issue type, not all the issues available in Project B.

The list of possible issue types is of course all the issue types the target project has in it, but it is limited by the general type.  If your current issue type is a sub-task, it will only let you move to sub-task types that are in the target project.  Similarly, issue-level issues can only be moved to issue-level types.

0 votes
Pramodh M
Community Champion
January 20, 2022

Hi @DEJU ALIN MADALIN 

Here are troubleshooting areas

Did you check the initial workflow of project for other issue types.

Check the standard issue type and sub-task issue type.

Here's the reference link for further troubleshooting

https://community.atlassian.com/t5/Jira-questions/How-to-move-an-issue-from-project-A-to-project-B/qaq-p/963883

Thanks,

Pramodh

0 votes
Bibek Behera
Community Champion
January 20, 2022

@DEJU ALIN MADALIN 

 

Do you see any error during the operation? How many issue you have selected for the move and are all the issues of the same type? I would consider reindexing once and give it another shot.

 

-Bibek

DEJU ALIN MADALIN January 20, 2022

Hello @Bibek Behera ,

Only one issue I'm trying to move. Also, I don't have any errors.

(Strange is that the workaround using Bulk is working)

 

But I've noticed that the issue could be from a Behaviour that hide some issue-types from Project A.

 

Best regards, 

Alin