Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Muliple "Done" Statuses

frank lohfeld August 12, 2019

Hi, i have t statuses
"Done" and "in Review"

Anmerkung 2019-08-12 223818.png

Booth with the category "Done" in Workflow.
I wan't to reach that Issues in Status "in Review" also decrease the Burndownchart. But this doesn't worked. How can i build that in this way that i have two columns in sprintboard and booth columnes set a issue as down and decrease the burndown?

1 answer

2 votes
Jack Brickey
Community Champion
August 12, 2019

if you want two statues that are considered as DONE in a scrum board then both must be in the right-most column.

Suggest an answer

Log in or Sign up to answer