I am managing a project with multiple teams. Each team sets up it's own sprint.
While I have been successful in setting up dashboards for the individual teams, I have had some difficulty in setting up a dashboard that shows a rollup of the teams.
For example, the "Sprint Health Gadget" will only allow me to view one "sprint" at a time rather than allowing me to see the progress of all the teams together.
The biggest thing I am trying to see is a view story count with status on one axis and scrum team on the other access.
Any thoughts on pulling this off?
Cheers.
Hi JD,
Regarding your example , you can add "Sprint Health Gadget" multiple times in the same dashboard and this will allow you to select current sprints for all project
For your specific requirement i recommend one of the following approach :
1- You can use issue statistics gadget with "status" and this will give you count of issues/status according to your filter. you will need to create filter per team in this case
2- You can try easyBI/arsenal dataplane.
I hope this will help