I am curious if you plan to support multiple sprint in the Rapid Board. We have many projects, but I seem to be able to only build 1 sprint into 1 project at a time. I may have multiple sprints underway at the same time within the same project, based on available resources, but it seems like the Rapid Board can only deal with 1 sprint at a time.
I understand I could completely alter my project set up, but I feel like the reporting would be completely invalidated.
Any thoughts?
With the release of Parallel Sprints the answer is that you can now run more than one sprint at a time on a single board.
This answer is not entirely correct. You can only start a sprint on a board if none of the issues matched by the filter are currently in a sprint. You must carefully slice your issues by filter so that there will not be any overlap.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kenneth,
you can create multiple rapid boards based on different search filters. Then you can start a new sprint with each rapid board.
Cheers
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.