Multiple performers

Александр А.
Contributor
December 24, 2019

Good afternoon, please suggest:
1) How do you set up multiple performers for a single task?
2) How to set up and install automatic follow-up task activation (next task)

 

 

https://yadi.sk/i/1zamwV59llqc4Q

 

 

https://jira.*****ech.ru/projects

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 24, 2019

You do not have multiple assignees.  Jira has a single assignee, as multiple ones do not work in real life.  The assignee is the one single person who should be responsible for the issue in its current state.

You can include other people as "interested" or "the backup responsible person" etc.  Use the watchers field possibly, or maybe a group-picker if you know it's going to be a member of a particular group, but most use a custom field of a user picker.

Or create sub-tasks, assigned to the people who are responsible for doing their parts of the task.