Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Multiple timelines/phases per epic in advanced roadmaps

Deleted user August 10, 2022

Is it possible to showcase different phases for one epic in the timelines section of advanced roadmaps? For more detail, can I showcase multiple timelines for Ideation, Requirements, Design, Development per epic in the roadmap?

1 answer

0 votes
Mark Segall
Community Champion
August 10, 2022

Hi @[deleted] and welcome to the community!

Roadmaps are purely about start and end date of a given issue.  I would recommend using a Task for each workflow step under the epic.  Then you can just expand the epic to see the expected timeline for each phase. 

You could take it another step and clear out the Target Start/End date of the Epic and track the time against those phases so that you have the ability to dynamically set the Epic timeline based upon whatever is set on the individual tasks.  

Lastly, you can create a view that filters out everything except your phase tasks so that when you're talking about things at a high level, you're looking at the Epics and their phase tasks.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events