Neat Gen project issue

koteswararao
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 1, 2019

Not sure what is going on . i created a next-gen project type.

Then their stories cannot break down into tasks ( or subtasks) . I looked at it but I don’t see the field to make it a parent relationship.

Can you help us out ?

It should be epic – stories – (sub) task  ( not picky which way ) but they need to be able to break it down.

1 answer

1 accepted

0 votes
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 1, 2019

Hello,

For next-gen projects you can use only the Epics -> Stories hierarchy. Subtasks are not available for next-gen projects.