I am struggling with the new view of subtasks. I do not see a way to delete a sub task as the current view allows.
We esitmate using hours and time tracking. In the current view I can easily enter original and remaining esitmate as fields. These seem to be out of the current implementation.
Is this considered a completed implementation? Thhere seems to be basic things missing.
Hi @Scott Ocamb
+1 for Original and Remaining - totally agree that this needs to be added to the new view.
To delete a subtask, open it (either in a new tab or as a pop-up from the board) and click on the 3 dots in the top right hand corner. There should be an option there to Delete
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.