No Board Settings for Work Management

Santhosh Raj
Contributor
October 24, 2023

Hi Team,

Story,
I have a Project with 1 year of Data and  I wanted data from October till present should be shown in that project.
But there is no board settings.
I have created a filter for that, but its not working.


How to make the board view to show issues only from Oct and hide the Issue data before October ?
Also I'm trying a Work Management -> Project Management -> Team Managed.
So is there an possible ways for achieving it either by settings or by Jira Automation ?


1 answer

1 vote
Walter Buggenhout
Community Champion
October 24, 2023

Hi @Santhosh Raj,

Your observation is correct: there is currently no way to filter the board view on date ranges and there are no board settings available to add your own filters. This may - to a certain extent - be because the goal of your board view is to mainly manipulate all open work (regardless of when it was created) towards completion.

While the date range filter is not available in the board view (by design, as mentioned in this support article ) This filter capability is currently already available in the list, timeline and calendar views of your project, where you can apply date filters:

2023-10-24 13_33_31-List - Business Task Manament Demo - Jira.png

You can share your suggestion with the product team via in product feedback:

2023-10-24 13_42_00-.png

Hope this helps!