I created a Project in Jira and RoadMap. At BigGantt I'm mapping overall activities and timelines. But Status, Task Progress and Completion columns are appearing in blank. Is there something else I have to set, configure, add or something else?
Are your Jira Issues coming into the BigGantt? Did you follow all of the steps here:
https://wiki.softwareplant.com/display/DOCUMENTATION/Gantt+configuration
and, you won't see Task Progress until time has been logged to the Jira Issue.
Can you please post a screen shot?
Hi, thanks for your reply. Yes, it's configured like the link you sent... Can you elaborate more on " and, you won't see Task Progress until time has been logged to the Jira Issue."?
Below my printscreen. Sorry handdrawing is not got. But highlight both information missing...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
for Time Tracking, time must be data entered into Jira on the Task or Story in order to show progress. I am not sure, but I think you also have to have the Original Estimate field populated in Jira so that BG can do the % complete. Has anyone logged any time on any of the Tasks?
https://confluence.atlassian.com/jirasoftwarecloud/logging-time-on-issues-902499028.html
For Status, first: check in Jira that the Tasks have a workflow, with statuses. Then: verify in Jira that each Task actually has a status. If you can see the status in Jira, but not in BG, then I'd guess that you're pulling the wrong Status field into BG.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
- I am not sure, but I think you also have to have the Original Estimate field populated in Jira so that BG can do the % complete. Didn't find where to put original estimation in hours. just in points... know where?
- Has anyone logged any time on any of the Tasks? Logged option doesn't appear to me ! need to activate somewhere this field?
- For Status, first: check in Jira that the Tasks have a workflow, with statuses. it has status. Workflow? is that activity list?
- If you can see the status in Jira, but not in BG, then I'd guess that you're pulling the wrong Status field into BG. I added the only two Status fields I found. None of them are working.
Any other tip?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.