I am not able to complete the sprint. All the tickets in the sprint are in Done Status. Still, when I try to complete the sprint it says, issues are open. There are no linked issues and nothing like any blocker.
The below pop-up is shown
This sprint contains:
It doesn't sound like the following is your problem, but Jira will not let you complete a sprint if any work items are in a status mapped to the far-right column that have sub-tasks under them which are not.
Basically, open sub-tasks on a closed work item will prevent the sprint from being completed.
Hi @Abhishek Sisodia ,
Regards,
Yousuf
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.