  • On my Scrum Board, when using 'Base Swimlanes on Epics', the Sub-Tasks that are directly under Epics are shown under 'Issues without Epics'

On my Scrum Board, when using 'Base Swimlanes on Epics', the Sub-Tasks that are directly under Epics are shown under 'Issues without Epics'

Gowri Kumar April 25, 2016

This question is in reference to Atlassian Documentation: Configuring Swimlanes

On y scrum board, when using 'Base Swimlanes on Epics', the Sub-Tasks that are directly under Epics are shown under 'Issues without Epics'. How can I make it show under the Epic it has been created for?

 

Thanks

2 answers

0 votes
Deleted user April 25, 2016

Nic's correct, note the message on the Edit screen of a sub-Task;

image2016-4-25 7:17:29.png

Since a sub-task can not be assigned to an EPIC, you get the very results you have identified. Yes, the EPIC is the parent issue, but JIRA does not see the Parent as an EPIC because of the notice above.

Use Nick's solution to resolve this problem.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 25, 2016

Move them to stories under the epics.  Epics are not really the right place to create sub-tasks.