Hi there, i encoutered a probelm with my project roadmap.
I have 3 sprints in the project while Sprint 2 is missing in the project roadmap.
Checked all issues in the 3 sprints belong to the current project and the start date and end date have been set.
Sprint 1: 31/Jan/22 3:55 PM -> 13/Feb/22 3:55 PM
Sprint 2: 14/Feb/22 3:55 PM -> 27/Feb/22 3:55 PM
Sprint 3: 28/Feb/22 4:49 PM ->13/Mar/22 4:49 PM
Due to previous settings, Sprint 2 is the current active sprint (not completed) and the sprint 1 is not started.
So is it because the historical sprint has not been completed?
If so, how can i make sprint 2 appear in the project roadmap?
thanks a lot!
I have found that is because I created a Sprint from a different Board. If you have multiple boards, my recommendation is check those and see if your missing Sprint is there.
On a side note, this is something that seems like a bug for me, even though I create multiple boards, I should see the same Sprints through all.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.