Only one sprint can be started at the same time?

Chris Zheng August 8, 2018

Hi community,

I created two sprints and one had been started. I couldn't start another sprint as the "Begin Sprint" button is unavailable. Is that mean only one sprint can be started at the same time?

Thanks.

1 answer

1 accepted

2 votes
Answer accepted
Ollie Guan
Community Champion
August 8, 2018

Hi @Chris Zheng,

The system administrator can open Parallel Sprints as follows,allows a new sprint to be started when one is already in progress.

https://confluence.atlassian.com/jirasoftwarecloud/using-parallel-sprints-797737030.html

sprint.png

Chris Zheng August 8, 2018

Wow, it works. @Ollie Guan Thank you so much!

In addition, there are some issues in one sprint, and do you know how to set up a start-time and an end-time for each issue? 

Thank you!

Ollie Guan
Community Champion
August 8, 2018

Hi @Chris Zheng,

The start and end time of the sprint is for all the issues in the sprint,

If you want to set a different start and end date for each Issue, you can customize some datetime type fields, or you can use a plugin that implements the Gantt chart function.

e.g

https://marketplace.atlassian.com/addons/app/jira/top-selling?hosting=cloud&query=gant

Chris Zheng August 8, 2018

@Ollie Guan I see. Thank you very much. Have a nice day.