Original time estimate not rolling up

Maroun Maroun February 24, 2023

I think I'm misunderstanding the original estimation on stories.

I have a story, with a number of subtasks. All subtasks have an "original estimation". The rolled up value shows only in "time tracking", but the original estimate is not summing up.

 

image (22).png 

Is this intended? If not, how can this be fixed?

1 answer

1 accepted

2 votes
Answer accepted
Mikael Sandberg
Community Champion
February 24, 2023

What you see is expected behavior. You should not have estimate on subtasks, that stays on the story level, all based on scrum principals and that is what Jira is following. You can see further explanations in this thread. It is only time tracking that will roll up to the story from subtasks.

Maroun Maroun February 25, 2023

 

@Mikael SandbergMy perspective on subtasks and stories has been completely altered. What is the suggested approach for estimating a story? Should one create all subtasks first and base the estimation of the story on them? I mean, subtasks are essential for having an estimation on the story. I'm just curious about the best approach for planning in this case.