Hi
I'm looking for the most efficent way to track planned vs actual within advanced roadmaps. We do the majority of our planning from an epic level with the delivery team doing a deeper dive at story level and I want to be able to show changes to the plan at the end of each sprint.
The only option I could see was to create a new scenario - one showing what we planned at the start of the project and one showing the live version but ideally I want to be able to see these next to each other so we can see what took longer than planned and what was quicker.
Any advice would be great
I have the same "problem". There is a solution?
Create a second plan using actual date (start and end)?
- Planned use target start and target end
- Actual use actual start and actual end
I am interested in this as well, can't find anything on this
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No one is responding for Jira queries for plan v/s actual tracking, i don't know, why?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.