I have a large number of items in my portfolio. I need to filter it to be able to edit (e.g. set dependencies) child items.
The very first item in my scope view has a scheduled start of 2/21/17 and a scheduled end of 3/7/17. That means all children items must complete during that timeframe, right?
When I select the More->Scheduled Range filter, and select a range of 2/1/17 to 3/31/17, I only see two of the 10+ child items.
Portfolio 2.2.2
I was able to resolve this. I had set an invalid dependency on one of the child items (it was dependent on the completion of it's parent). That prevented the Portfolio scheduler from being able to schedule that task and all subsequent tasks that were dependent on it. So although the the epic had a scheduled end date, it wasn't based on completion of all the child tasks.
I'm not sure why portfolio allowed me to set the invalid dependency or at least warn me about it, but in the end the mistake was mine.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.