Hello,
We have come across many issues upgrading JIRA agile 6.2 to 7.1. The question is if this migration path, to a different server (on prem) is actually supported at all.
Thanks!
Asaf
Yes, it is supported, but if you're struggling, I'd recommend taking smaller steps - get it to Agile 6.7 first, then make the smaller jump from Agile to Software.
Thanks!
Went through 6.1.4 and it seem to work better for us.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Nic,
I just realized we are trying to make two things,
Would it be better for us to do it in two steps, i.e. migrate to a new server running 6.2 and then upgrade to 7.1? What do you think?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It depends on your business plans.
Moving it has the huge advantage that if something goes wrong during the plan, you can just go back to using the old system (because it's less a move than a "copy it to new place"). But if your business needs very short outages on the system, then you'll probably want to do it in several steps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.