Prevent Transition of Epic if Sub-Tasks not in Done Status

Maritsa Annandale February 8, 2021

Hi

Can automation be put in place to prevent the transitioning of an Epic if the Child Issues below the Epic is not in Done Status?
We are using a Next-Gen Project?

 

1 answer

0 votes
John Funk
Community Champion
February 8, 2021

Hi Maritsa - Welcome to the Atlassian Community!

Automation for Jira cannot prevent an action from taking place - you need to handle that in the workflow.

Edit the workflow to add a condition to the transition to Done. 

But you are probably going to need an add-on like JMWE to be able to prevent that. 