Hi,
Earlier I had a workflow as shown in the below figure and it was used by all the projects,
Then we changed the workflow as the below now the below workflow is used by every project,
When we using the previous workflow, in sprint view of boards, all done tickets were shown by a strike-through on ticket IDs as shown in the below figure,
But after changing my work flow I need to display "Verified" tickets with strike-through. But still it displays "Done" tickets with strike-troughs. How can I change this?
The tickets with strike-troughs depend on the value of resolution
You can modify the workflow when resolution = done if the state is Verified