Problems with field Story Points in JIRA

Anas Ibrahim
Community Champion
November 25, 2019

We are having problems with the displaying the field Story Point in JIRA Software 7.6.2 in Sprint Report & Burn Down Chart

Problem description 1

1. Person 1 (Ruben) enters value “5” at issue ETSYS-716 in field “Story Points”
--> Estimation is displayed correct in Sprint Report and in Burn Down Chart for all users

2. Person 2 (Matthias) edit value from “5” to “10” at issue ETSYS-716 in field “Story Points”--> Estimation is displayed wrong in Sprint Report and in Burn Down Chart

3. Person 3 (Michael) sees now the value “-“ in Sprint Report and in Burn Down Chart for this issue

Problem description 2

1. Person 1 (Ruben) enters value “10” at issue ETSYS-1755 and ETSYS-1756 infield “Story Points”
--> Estimation is displayed correct in Sprint Report and in Burn Down Chart for all users

2. Person 1 (Ruben) edit value from “10“to “4” at both issues in field “Story Points”
--> Estimation is displayed wrong in Sprint Report and in Burn Down Charti
-> Person 2 (Michael) sees the old value “10“ in Sprint Report and in Burn Down Chartfor this issuei
-> Person 1 (Ruben) sees the new value “4“ in Sprint Report and in Burn Down Chart for this issue

 

Please help to understand this behaviour or solve this issue.

Regards,

Anas.

 

0 answers

Suggest an answer