Hi, I have the issue that my Product Owners cannot start a Sprint in Scrum Boards.
My settings are set this way:
Still my POs cannot end or start sprint, only I as Admin can do that. Could anyone help me to review the settings and get this sorted out please?
Hi,
Can you look if there's multiple project in the scrum board. May be they don't have the good permission in thoses projects.
I have two projects in the board and both use the same permission scheme
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.