I'm evaluating Tempo to see if it can replace our current system for traditional task and project planning (not Agile). To manage the IT portfolio right now, we use MS Project and a series of spreadsheets that require manual intervention to keep the two synchronised.
JIRA and Tempo have ticked a lot of boxes so far, but as far as planning goes, I've found lacking in some key areas. For example:
I've had some difficulty integrating / importing between Project and JIRA, but those are separate issues. I'd love to know: is there an add-on or plugin for JIRA that allows for efficient project planning?
I'm not talking multi-year, thousands-of-tasks projects - more on the 3-6 months, 1-200 tasks scale.
BigGantt is pretty darned nice
BigPicture is BigGantt plus a Resource Model, so even closer to MS Project
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chris,
There is also the option to keep MS Project and use it with JIRA and Tempo. You can integrate them with the help of Ceptah Bridge. You can do all your planing, scheduling, dependencies and re-scheduling in MS Project and then reflect that all in JIRA. You can also track progress in JIRA with Tempo and then import it to MS Project, re-schedule tasks and put the changes back to JIRA, e.g. new Due Dates. Once set up, the synchronisation will require only a couple of clicks in Ceptah Bridge.
Cheers,
Sergey
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please take also a look at https://www.youtube.com/user/tempoplugin
The videos about Tempo Planner might give you some more information about available features and possibilities.
Regards,
Susanne
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chris,
You might also want to look into JIRA Portfolio, which is an "agile portfolio management tool, built for JIRA" by Atlassian themselves. You don't have to use it in an "agile" fashion if you don't want to. I don;t know what your speed requirements are, but for project management using JIRA work items it's pretty good.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.