Hello,
I hope my question will be clear.
Situation: we work on 2 weeks' length sprints. QA team test one sprint behind. Meaning, when the issue is moved to 'Done' and Sprint is Closed, they start testing those issues.
I need to close the sprint and move issues to Done, as otherwise will not have a burn-down chart and see what's been done.
Problem: QA is working (testing issues which were completed last sprint) on a Closed sprint, and I cannot move those closed issues into a current sprint. Neither I can (at least I think I can't), create a separate Sprint for QA, where they will test those 'Done' and Closed items from the previous sprint.
What I do now is - create a separate filter for them, but there they see the only status in Done. Because I cannot set up a filter with other statuses of those issues, as they are already completed in the last sprint and my filter shows only the current sprint. I am a bit lost, yet I bet there is a smarter way to fix it.
Expected result: How to set up Software project board, filter and/or sprint so that QA would have a smooth testing process, when testing one sprint behind and would not need to get lost.
Thank you,
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.