Hi,
We have a questions on Burnup and BurnDown charts
1. Is it possible to turn off the counting of sub-task as part of the work scope on Burnup/BurnDown charts.
2. Is there a report available that would show the average BurnUp/BurnDown per team ?
Thank you in advance.
1. depends on the estimation technique you are using, and the config of the report - what are you using?
Have a look at:
https://www.atlassian.com/agile/tutorials/burndown-charts
https://support.atlassian.com/jira-software-cloud/docs/view-and-understand-the-burndown-chart/
You might be able to tweek the report with your estimation and report configs.
Or, you could create a new board with a filter that excludes sub-tasks - reports use the board filter.
2. https://community.atlassian.com/t5/Jira-questions/How-to-see-velocity-chart-report-of-all-sprints/qaq-p/835226, might give you what you need.