Question on Plans-plugin (Advanced roadmaps)

AMIT GULATI
Contributor
April 3, 2025

Hi,

 

Anyone knows what these numbers (15 and 9) on the Gantt chart indicate in JIRA Plans (Advanced roadmaps). I tried looking in the documentation but couldn't find anything.

 

Plans Gantt.PNG

1 answer

0 votes
John Funk
Community Champion
April 3, 2025

Hi Amit,

Can you provide a bigger view? What is this line for example? 

Also, are you using any plugins for the Gantt charts? 

AMIT GULATI
Contributor
April 4, 2025

Hi John,

The view contains the portfolio epics -> program epics -> features for an ART. This line is for one of the program epics. And I see it only for just one program epic. Unable to figure out, what makes this epic different from others.

 

I am just using Advanced roadmaps plugin over JIRA.

 

Br

Amit

John Funk
Community Champion
April 4, 2025

Hmm, that's strange. You might want to ask Atlassian that question. 

https://support.atlassian.com/contact/#/

AMIT GULATI
Contributor
April 4, 2025

Alright. Thanks John.

Like John Funk likes this
John Funk
Community Champion
April 4, 2025

Please post back here with any solution you end up with. 

AMIT GULATI
Contributor
April 9, 2025

John, It was the dependencies of the issue. Typically, they show up in front or back of gantt bar but due to lack of space, they showed up inside the bar.

Like John Funk likes this