Hi,
Anyone knows what these numbers (15 and 9) on the Gantt chart indicate in JIRA Plans (Advanced roadmaps). I tried looking in the documentation but couldn't find anything.
Hi Amit,
Can you provide a bigger view? What is this line for example?
Also, are you using any plugins for the Gantt charts?
Hi John,
The view contains the portfolio epics -> program epics -> features for an ART. This line is for one of the program epics. And I see it only for just one program epic. Unable to figure out, what makes this epic different from others.
I am just using Advanced roadmaps plugin over JIRA.
Br
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hmm, that's strange. You might want to ask Atlassian that question.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
John, It was the dependencies of the issue. Typically, they show up in front or back of gantt bar but due to lack of space, they showed up inside the bar.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.