Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

RTE in Burndown not showing zero hrs at the end of sprint

Buck
Contributor
December 2, 2019

My burndown chart is not showing zero hours at the end of sprint.  I've poked around and found a similar post HERE.  

RTE issue.pngAll of the issues were completed in sprint.  Nothing was passed to the next sprint.

Below is a picture of the Burndown using Story Points.  You can see everything was completed.

burndown story points.pngI have checked at my project standard workflow (used by multiple teams) has the RTE set to zero as the first post function. 

rte workflow.png

Any help is appreciated.  Thank you

 

0 answers

Suggest an answer

Log in or Sign up to answer