Hi,
We have two scrum boards which we want to use on two different sprint schedules but for some reason when I close a sprint on one board it closes both of them.
Each board had it's own stories and tasks with no cross over that I could see.
Is there a way I can run different sprints for each board?
Regards,
Luke
Hi, Luke.
What probably is happening is that you have the same sprints for both boards and since the boards have different filters (for example, filters per projects with different projects for each board) you see mostly different issues for the different boards. When you close one sprint, it is closed in the other board.
A sprint will appear in every board that contains an issue that it contains, as you can read here: https://confluence.atlassian.com/display/AGILE/Working+with+Sprints.
You can search for the issues of this sprint by the sprint ID and see if the issues include issues from both boards.
I hope it was helpful.
Kind regards.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.