Hey is it possible to add the timetracking field inside the Jira plans overview? Somehow i cant find the field in the configuration setup directly or in the custom fields section inside my plan settings.
Am i missing something or is it just not possible?
Greetings!
Hi Lukas,
Time Tracking is really a set of three fields - Original Estimate, Time Spent, and Remaining Estimate. So look for those fields.
You can find the field with original estimate and Time remaining
if you add Time tracking field in the screen then it will show as original estimate and time remaining
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Welcome to the Community,
Please refer to this article which can give you details on the original estimate field in jira plans : https://confluence.atlassian.com/jirakb/i-cannot-find-the-system-field-original-estimate-in-jira-plans-advanced-roadmaps-1384122329.html
If you wish to show the Orginal Estimate Field, as a workaround add a custom field to the Plan that copies the value from the Original Estimate using Automation for Jira. However, this will not allow this custom field to be taken into account when it comes to the scheduling in the Plan. But this would allow us to view the value of the live plan.
Thank you,
Prachi