Adding Half non-working day?

Noam Inbar
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 14, 2020

Hi,

In several cases we have weeks with "half-holiday", meaning tea is working half day.

I do not want to add "Full non-working day", and want to see an accurate burn-down chart.

For that, I would like to add "half non working day". I did not find option for that.

If someone has other ideas that keeps burn down accurate, I would be happy to hear.

 

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 29, 2020

Hi @Noam Inbar 

I could not find a way to do that either.  There are several open suggestions related to this.  Please take a look and vote for any that you find valuable. If you do not find a match to your question, you can add a new suggestion.

https://jira.atlassian.com/issues/?jql=project%20IN%20(JRACLOUD%2C%20JSWCLOUD)%20AND%20resolution%20%3D%20Unresolved%20AND%20summary%20~%20working%20%20AND%20summary%20~%20hours%20ORDER%20BY%20Key

Best regards,

Bill